THE 20-megawatt (MW) Maibarara-1 geothermal strength facility (Maibarara-1) in Batangas received the Geothermal Power Project of 2016 award at the Asian Power Awards held remaining September 21, in Seoul, South Korea, the operator of the plant said on Monday.

The Asian Power Awards, now on its 12th 12 months, is taken into consideration the Oscars of the energy industry in Asia, recognizing ground-breaking tasks and trailblazing initiatives within the strength quarter.

The Maibarara-1 facility in Sto. Tomas, Batangas is owned and operated with the aid of Maibarara Geothermal Inc. (MGI), a joint project among PetroGreen Energy Corporation (PGEC) with 65 percentage), Phinma Energy (with 25 percent), and PNOC-Renewables Corporation (10 percent).

PGEC is a subsidiary of publicly-listed PetroEnergy Resources Corporation.

In a disclosure to the Philippine Stock Exchange (PSE) on Monday, MGI stated the award acknowledges Maibarara-1’s modern improvement, powerful operations, and dynamism inside the area of geothermal strength.
Building on its a hit beneath-budget completion in February 2014 most effective 2.5 years from economic close, MGI has sustained  years of worthwhile industrial operations.

“This award suggests that Filipino know-how and ingenuity in geothermal strength operations are second to none.
Such global reputation of MGI’s facility in just two years of industrial operations owes to the imaginative and prescient and awareness of our Board, the determination and professionalism of our team, and the engagement and cooperation of our stakeholders in regulatory companies, non-public enterprise, and host communities,” MGI president F.G. Delfin Jr. Stated in a assertion.

In 2015, MGI became able to reduce unscheduled shutdowns and to boom load nomination and internet technology from the lender-committed 18.5 MWe to 18.8 MWe. This led to will increase in availability aspect from 95.7 to ninety eight.2 percentage, internet potential thing from 89.Five to 91.8 percent, and internet income by means of 28 percentage as compared to 2014.

In addition, MGI also showed a bigger geothermal reservoir in Maibarara with the a hit step-out drilling and of completion of nicely MB-15D, which has at the least ~6 MWe output.

MGI is presently building the steamfield and strength plant components of Maibarara-2, a 12 MWe expansion in the current evolved web page aimed for business operations by using past due 2017.

This extra funding comes after MGI secured a P1.4 billion loan with Rizal Commercial Banking Corporation and signed an extended-time period energy sales settlement with Phinma Energy in January 2016.

MGI has shrunk Fuji Corporation of Japan to construct and deliver the turbine/generator for Maibarara-2, currently the handiest active creation of a brand new geothermal power plant inside the u . S ..